SIU Carbondale outlines Saluki Village P3 housing plan; foundation to fund demolition and initial work
Summary
University presenters described a public‑private partnership to replace derelict Old Greek Row with nearly 900 new beds, special‑interest homes and a community building; the SIU Foundation would fund initial demolition and hold easements to enable a rapid schedule.
Get email alerts on the Campus Development topic
No spam. Unsubscribe anytime.
Southern Illinois University Carbondale officials and the SIU University Foundation presented a proposed public‑private partnership (P3) housing project to the Board of Trustees on July 10, 2025 that would replace Old Greek Row with a planned student community of roughly 898–1,000 beds and auxiliary facilities.
The project concept: university presenters described an approximately 17‑acre site on Old Greek Row currently occupied by multiple vacant and boarded buildings. The proposed Saluki Village concept includes about 898 new beds, a community building and four to five special‑interest houses. The SIU University Foundation would act as an intermediary and provide upfront funding to demolish selected structures and to grant easements to allow the foundation to manage demolition or contract for demolition and subsequent development.
Timeline and next steps: presenters said they will return to the board with design and construction details in September and that the development team was working against a tight timeline with a target move‑in date cited for late August 2025 (August 27 mentioned as a goal in committee discussion). Trustees voted to place the project approval item (item z) on the omnibus motion for board approval, meaning the project received committee approval to move forward in the packed agenda.
Why it matters: The plan would replace dilapidated housing stock near campus with modern student housing and community spaces and could materially affect on‑campus bed capacity and student life. The foundation’s upfront capital role shifts early demolition and site control away from university capital budgets, but the project will require subsequent design, approvals and funding decisions.
What board members and staff said: Trustee Simmons (architectural & design committee) and campus facilities leaders outlined the rationale and the potential for the foundation to “accelerate” the project. Presenters noted Old Greek Row contains multiple abandoned buildings and that Collier Hall is among the remaining active structures; the project would clear the footprint for new construction and relocate foundation offices as planned.
Outstanding details: presenters and trustees said they will return with final design, financing, ground‑lease or development agreements, and an implementation plan. Because the foundation is providing initial capital for demolition and easements, the board packet identified the need for subsequent board approvals before construction contracting and occupancy.
What’s next: Further design and budget approvals are expected in September 2025; staff said they will provide more detailed project budgets and timeline updates to the board when available.