Summary

City public-works staff reported a contractor struck a 4-inch culinary main at 95 East / 340 North and outlined a planned reroute to keep the main at least 10 feet from nearby structures; parts are being ordered and repairs are expected once fittings arrive.

City public-works staff reported two separate water problems and outlined repair plans and scheduling needs.

A contractor installing posts at 95 East and 340 North struck a 4-inch culinary main, staff said. The city closed valves to isolate the line and proposed rerouting a short segment of main to keep the pipe at least 10 feet from the shop edge; the fix would add roughly four lengths of pipe and involve working through private yards and existing utility easements. Staff warned that the GPS location for the existing main is off by roughly 20 feet and that the easement runs through backyards and fence lines, so the crew will confirm easement width before excavation.

Public-works staff said suppliers did not have the needed fittings in stock but could order them; the speaker said the work could begin as soon as parts arrive and that, realistically, crews may start the repair on a Monday when parts are on hand. The city also plans to schedule valve shutoffs and give residents advance notice because the repair will likely take most of a day.

Separately, staff reported a leak on Main Street tied to a broken service line to an abandoned property at 155 North (former gas-station service). The leak persisted for several days while the city waited for a Blue Stakes locate and non-emergency contractor availability; staff said water was shut off for less than an hour to complete the fix once the crew could work.

Other operations updates • Potholes: staff plans roughly a week of coordinated pothole repairs using hot mix; crews will stage multiple repairs and bring asphalt loads to avoid working with cold material. • Street sweeping and mowing: staff asked for timing guidance ahead of the city’s large July celebration and parade and recommended sweeping a few days before the event (the Friday before). • Wood-chipping and green-waste pile: crews continue to chip the large pile; staff said the city is paying for the work and will retain the chips for future use.

Direct quote: "I don't think a main should run anywhere near a building. So keep it 10 feet away from the edge, then it'll put us, like, dead center of our easement," said Garrett, the public-works speaker describing the repair plan.

Staff said they will provide scheduling updates to the contractor building the shop so that construction work can be coordinated with the repair timeline.