Council hears multiweek Arlington Avenue sewer repair timeline; city seeks $500,000 to finish O'Gods pumping station
Loading...
Summary
Public Utilities described a planned 55-foot shaft excavation and bypass pumping to repair a failed sewer pump on Arlington Avenue and asked council to appropriate $500,000 to complete engineering and construction for the O'Gods pumping station.
The Toledo Department of Public Utilities updated council on emergency sewer repairs on Arlington Avenue and requested $500,000 to finish the O'Gods pumping station project.
Director Doug Stevens said contractors will excavate a deep shaft roughly 28 by 17 feet and 55 feet deep to install a bypass and a large pump to handle wet-weather flow; site mobilization would begin within days and construction work is expected to continue into December. "It's gonna take about 3 weeks to dig it ... that whole process is expected to take into December. It's gonna be a full 6 months of doing this," Stevens said, describing excavation, bypass pumping, cleaning and televising of sewer lines, and a final structural liner installation. (Doug Stevens, Director, Department of Public Utilities)
Stevens warned council that without the permanent pump, Maumee Sewer could charge what the city considered "excessive" fees if the city continued to discharge flow to that system; the O'Gods engineering, construction oversight and construction costs are now estimated at $1.25 million, with $750,000 appropriated. The department asked council to appropriate an additional $500,000 to finish the project this year so the city can separate about 77 homes from the Maumee sewer system. "We only have $750,000 appropriated ... to this point. This legislation would be to appropriate $500,000 so that we can make sure to complete that pumping station in a timely manner and avoid ... excessive charges from Maumee," Stevens said. (Doug Stevens)
Officials also described the public-health context: the administration continues E. coli advisories for affected creeks and said readings have been trending downward when overflows do not occur. Stevens said the boil/creek advisories will likely remain in effect until wet-weather overflows are fully addressed and the bypass pumping is in place. Council members praised on-the-ground crews for continuous monitoring and outreach to nearby residents, and asked for direct constituent communication about excavation and restoration timing.
In related items, Stevens described an emergency repair at the Water Reclamation Facility to clear a blockage in a digester and presented a request to enroll 12 new water-reclamation vehicles in the Samsara fleet telematics subscription for maintenance and tracking. Stevens said the digester emergency required an unplanned scope and the request was to pay the difference to the emergency contractor so the city could close out the contract.
Why it matters: The Arlington repairs and the O'Gods pumping station affect neighborhood flooding and local water quality; delays or insufficient funding would risk continued overflows and potential large charges by adjacent sewer systems. Council members asked for frequent resident updates and confirmation that damage claims or yard sinkage issues are being addressed by field crews.
Next steps: Utilities requested SEP on the O'Gods appropriation; council asked for continued progress reports and constituent outreach as excavation begins.
