District project updates: Percy Julian site work, Park Crossing field house, South Lawn gym and Carver turf timeline
Summary
Volker and district facilities staff reported progress on major capital projects — Percy Julian High School site work, Park Crossing Field House, South Lawn Middle gym addition and Carver High turf — and identified an approximate $2 million cost associated with the Todd Road relocation that was built into the Percy Julian budget.
District capital-program managers presented project updates at the June 8 work session, reporting progress and a small number of unforeseen costs that were already accounted for in project budgets.
Percy Julian High School: Volker reported phase 1 (Todd Road relocation tying the existing road into the boulevard) was about 80% complete and expected to finish this month. The firm said the separate Todd Road work was factored into the Percy Julian overall budget but was reported as a discrete project for Department of Construction and Management (DCM) approval. The cost of the relocated Todd Road work was stated in the meeting at about $2,000,000 and, according to presenters, was already included in the Percy Julian budget.
Percy Julian phase 2: The contractor has received notice to proceed and mobilized;…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat