Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

District project updates: Percy Julian site work, Park Crossing field house, South Lawn gym and Carver turf timeline

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Volker and district facilities staff reported progress on major capital projects — Percy Julian High School site work, Park Crossing Field House, South Lawn Middle gym addition and Carver High turf — and identified an approximate $2 million cost associated with the Todd Road relocation that was built into the Percy Julian budget.

District capital-program managers presented project updates at the June 8 work session, reporting progress and a small number of unforeseen costs that were already accounted for in project budgets.

Percy Julian High School: Volker reported phase 1 (Todd Road relocation tying the existing road into the boulevard) was about 80% complete and expected to finish this month. The firm said the separate Todd Road work was factored into the Percy Julian overall budget but was reported as a discrete project for Department of Construction and Management (DCM) approval. The cost of the relocated Todd Road work was stated in the meeting at about $2,000,000 and, according to presenters, was already included in the Percy Julian budget.

Percy Julian phase 2: The contractor has received notice to proceed and mobilized; substantial earthwork, demolition of existing site structures and dewatering are underway.

Park Crossing Field House: Project reported as about 98% complete with a state inspection (substantial completion) scheduled; furniture and equipment installed and final inspections pending. District staff said the building should be ready for students for the 2025—26 school year pending the state inspector's final sign-off.

South Lawn Middle School gym addition: Project approximately 68% complete. The district reported change-order requests tied to unforeseen roof and utility relocations; a time-extension request was under review with the architect and the district. Window and exterior door installation was underway; HVAC units were scheduled to power up the next week to allow interior finishes to proceed.

Turf and track projects: Park Crossing turf and track were reported complete and already in use. Carver High School's turf and track required a change order because removal of the existing rubber track revealed subbase conditions beyond the contingency. Facilities staff told the board the work remained within the overall Percy/Carver program budget and the schedule continues to target field readiness for the start of school, weather permitting.

Minority participation: The presentation included minority-participation metrics: about 45% on professional services and about 4% on construction (the presentation slide noted those figures for projects in progress).

Why this matters: The updates outline expected completion timelines for major school projects that affect sports, instructional space and the start of school scheduling. The $2 million Todd Road cost was explicitly identified and told to be accounted for in the Percy Julian budget; South Lawn timeline could shift based on change-order reviews.

What the board asked: Board members asked whether concrete masonry walls at South Lawn would be painted and specific questions about the cost and schedule impacts of unforeseen work. Facilities staff answered and said contractors are using night and weekend work where needed and the district is scheduling final inspections with state reviewers.

Attribution: Reports and answers came from Volker project staff and district facilities staff (presenters identified as representatives of Volker and district facilities). Chad Anderson also described the Carver turf subbase issue during the public portion of the meeting before consent approval.