The Town Council voted unanimously to adopt an Americans with Disabilities Act (ADA) transition plan that lays out a multi-year program of surveys, repairs and upgrades; FY26 work will be funded from existing budgeted dollars, the presentation said.
Get email alerts on the Ada Transition Plan topic
No spam. Unsubscribe anytime.
The Indian Trail Town Council unanimously adopted the town's Americans with Disabilities Act transition plan during its council meeting, directing staff to implement the phased program using budgeted funds for fiscal year 2026.
The plan, presented to council by a staff member identified in the meeting as Mister McLan, documents a multi-year approach to identify and remediate barriers in the town's rights-of-way, parks and municipal facilities. "ADA is a civil rights law that is required by the federal government. The transition plan is a self assessment process that we go through, and then it's to continuously transition into a more compliant town," Mister McLan said.
The consultant Precision Infrastructure Management assessed roughly 100 miles of right-of-way and identified more than 14,000 barriers in a snapshot assessment, the presentation said. The overall estimated cost to repair the features identified at the time of the assessment was put at about $12 million; the presenter said that figure is a snapshot and will change over time as new defects appear and repairs are completed.
For fiscal year 2026 the plan called for roughly $450,000 in work. Mister McLan told council that the town expects to complete a mix of consultant-contracted work and in-house repairs and that no additional money beyond currently budgeted funds is being requested for FY26. "If we do some of that work internally . . . we can have a little bit of cost savings," Mister McLan said. He said specific FY26 priorities include repairs at the Crooked Creek playground, website accessibility work estimated at about $35,000, right-of-way repairs and park/facility upgrades.
Councilmember Clarence made the motion to adopt the plan. The motion passed by unanimous voice vote; the meeting record does not supply an itemized roll-call tally.
Council members asked how narrow sidewalk sections would be addressed; the presenter said many narrow sections are short and can be corrected by reconfiguring the sidewalk panel or pushing a short section slightly farther into the adjacent right-of-way rather than fully replacing long runs.
The adopted plan calls for ongoing re-surveys (about 20% of the town each year) so the town can continuously update its inventory of barriers and track progress. The presentation also emphasized that the plan is a multi-year program rather than a single-year fix and that the town must document ongoing progress to respond to potential complaints.
The council did not vote to appropriate additional funds beyond items already in the FY26 budget; the presenter said FY26 work can be completed with existing budgeted dollars.
The Americans with Disabilities Act transition plan will provide the town a formal grievance process and a prioritized list of repairs that staff will schedule across future budget cycles.