Summary

Board members said switchgear and generator charges pushed a project over earlier estimates and that the reconstruction fund and ARPA restrictions limit what can be billed; staff estimated low month-end balances without transfers.

Board members described recent invoices on a switchgear project and generator rentals that increased project costs and tightened available balances in reconstruction and related accounts.

A board member said an outstanding generator-rental invoice for about $6,110 and other charges pushed the project total to “just over $800,000” (board member described the figure as approximate). The board noted an initial $300,000 allocation from 2024 had already been used and that the reconstruction fund balance will be much smaller after the recent work.

Staff reported roughly $125,000 remained in an account identified during discussion and said the department spends at a rate that could deplete that balance if current outlays continue. The board moved and approved a transfer to cover sludge-disposal costs and avoid a negative balance later in the season.

Why it matters: board members said reconstruction funds come from district communities that use the wastewater facility, ARPA is a grant and therefore not billable in the same way, and other restricted funds cannot be repaid in the same manner. The transfer was described as a short-term administrative fix while the board monitors expenditures and year-end positions.

Next steps: staff will track month-to-month balances and report back; the board may consider returns to reconstruction if a surplus exists at year-end.