Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
Bath County board approves middle school site survey, tables two high-school roof change orders
Summary
The Bath County Board of Education approved a $16,500 site-survey contract for the Bath County Middle School renovation and voted to table two change-order proposals for Bath County High School roofing/brick repairs while staff seeks better pricing.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
The Bath County Board of Education on June 23 approved site-surveying services for the Bath County Middle School renovation and tabled two high-school change-order proposals while district staff seeks lower contractor bids.
The board voted to hire QK4 for site-surveying services for the BG-25-048 Bath County Middle School renovation project for $16,500, a motion moved by Carla and seconded by Barbara that carried on a voice vote. District staff had told the board earlier in the meeting that three quotes were returned for the BG-1 site survey, with the lowest quote described in the working session as $16,005; the board approved the QK4 contract at $16,500.
Board members also voted to table two change-order proposals related to the Bath County High School HVAC/roofing work (PR 34 and PR 37) to allow staff to negotiate lower pricing. PR 37 — described in the working session as masonry/brick weep repairs and related sealant work on the gym back wall — had an initial quote around $14,005.69. PR 34, a more extensive set of repairs tied to a long‑running kitchen/roof leak, was quoted at $76,002.77. The board moved to table PR 34 (motion by Barbara, second by Carla) and PR 37 (motion by Barbara, second by Carla); both motions carried on voice votes.
In the working session, district project staff reported the high‑school layback project was about 95% complete, with gym painting, epoxy flooring for locker rooms, and final HVAC/electrical balancing remaining. Staff said final inspections and an occupancy approval from Frankfort are pending; they estimated inspections likely the week after next but said some timelines depend on the HVAC contractor schedule.
Staff also briefed the board on funding and project closeout sequencing for LAVEC pavement costs: before paying those LAVEC charges the district must close out the high‑school BG-4 and BG-5 documents and reallocate funds via a revised BG-1 for LAVEC. Staff projected those administrative closings would likely occur in August after final high‑school pay applications are processed in July.
The board approved the site survey and took no final action on the two change orders; staff said they will continue negotiating and return with revised pricing.
Votes at a glance: approve QK4 site survey (BG-25-048) — motion carried; table PR 34 (BG22-376) — motion carried; table PR 37 (BG22-376) — motion carried.

