SFPUC wastewater quarterly: Southeast plant digesters near start‑up, headworks nears substantial completion
Summary
SFPUC staff reported progress on the wastewater program and Southeast plant major projects: biosolids digester construction at almost 80% complete, channel force main intertie over 65% complete, and the new headworks facility approaching substantial completion with demolition work already underway.
Bessie Tam presented the Water and Wastewater Enterprise quarterly report to the San Francisco Public Utilities Commission, highlighting construction progress, cost variances and project milestones for the agency’s System Improvement Program (SSIP).
Tam said the Southeast biosolids digester facilities project is past its peak construction phase and “we're almost at 80% complete in the construction phase, and the overall project is more than 64% complete,” with start‑up activities expected in 2026. She also reported the channel force main…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat