Trousdale County school field house foundation complete; masons working on block walls, trusses due in August

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff reported the field house foundation is finished, masonry is underway with four masons on-site, and trusses are on-site with a crane planned in August to set them; some exterior brick has been delivered.

Dr. Sandoval, a district staff member, updated the board on progress at the high school field house, saying the foundation took all winter and is now complete.

"They are laying block. They've got 4 masons on-site, met with the construction manager today, and they estimated it would take about 3 more weeks to finish laying the block," Dr. Sandoval said. He added some exterior brick has arrived and that trusses are on-site, with plans to use a crane in August to set the trusses.

Sandoval described planned reinforced block work (a continuous concrete/bulkhead pour with rebar) above each wall and supplied approximate wall heights: the wall next to College Street about 13 feet, a middle wall about 17 feet and the wall next to the stadium about 23 feet.

Board members asked clarifying questions and toured or reviewed recent photos; no vote was required on the update.