Trousdale County school field house foundation complete; masons working on block walls, trusses due in August
Summary
District staff reported the field house foundation is finished, masonry is underway with four masons on-site, and trusses are on-site with a crane planned in August to set them; some exterior brick has been delivered.
Get email alerts on the Field House Construction topic
No spam. Unsubscribe anytime.
Dr. Sandoval, a district staff member, updated the board on progress at the high school field house, saying the foundation took all winter and is now complete.
"They are laying block. They've got 4 masons on-site, met with the construction manager today, and they estimated it would take about 3 more weeks to finish laying the block," Dr. Sandoval said. He added some exterior brick has arrived and that trusses are on-site, with plans to use a crane in August to set the trusses.
Sandoval described planned reinforced block work (a continuous concrete/bulkhead pour with rebar) above each wall and supplied approximate wall heights: the wall next to College Street about 13 feet, a middle wall about 17 feet and the wall next to the stadium about 23 feet.
Board members asked clarifying questions and toured or reviewed recent photos; no vote was required on the update.