Emergency management director updates council on hazard mitigation plan; NRCS stakeholder meeting set for July 1
Summary
The town’s EMA director reviewed progress on the 29-item hazard mitigation plan, reported many items as completed or in progress, and announced an NRCS stakeholder meeting for July 1 on a Valley Lodge flood project. The council directed EMA to consult the conservation commission on wetlands-related mitigation items.
Get email alerts on the Hazard Mitigation topic
No spam. Unsubscribe anytime.
Richmond’s emergency management director presented an annual review of the town’s hazard mitigation plan during the June 17 meeting, summarizing progress and identifying next steps; councilors instructed staff to follow up with other town commissions.
The EMA director said most mitigation items are either completed, in progress, or being tracked; the report mapped each action from the 2022 hazard mitigation plan to current status. Notably, staff relayed that the Natural Resources Conservation Service (NRCS) has scheduled a stakeholders’ meeting tied to a PL-566 flood-mitigation project (Valley Lodge area) on July 1 at 10 a.m. at the community center. The director asked councilors to expect follow-up on that project and recommended publicizing the meeting to stakeholders.
Councilors asked specific status questions about elevated roadbeds, culvert upgrades, private-owner emergency action plans for dams, and dry flood-proofing of town hall records. The EMA director said some items remain low priority in capital planning and others require coordination with state agencies. Councilor Madnick moved, and the council approved, a direction asking the EMA director to reach out to the Conservation Commission to discuss three numbered mitigation items on the plan (items 14, 15 and 16 in the plan) related to wetland restoration and land protection.
The EMA director said the town’s debris-management, emergency operations, and other plans were being located and updated; some sensitive security details were not suitable for broad publication. Councilors asked staff to post the NRCS stakeholder meeting notice publicly and report back on river/stream-blockage reporting procedures.