Committee approves award for major rehabilitation at Ward Water Treatment Plant
Summary
The finance committee awarded PC Construction the contract to rehabilitate filters 1–4 at the Ward Water Treatment Plant after a rebid and value-engineering discussions; the project includes replacement of internal filter components and pipe-gallery repairs.
Get email alerts on the Water Treatment topic
No spam. Unsubscribe anytime.
Public service staff said the Ward Water Treatment Plant, brought into operation in the early 1980s, requires a full rehabilitation of filters 1–4 after detailed inspections found multiple operational issues.
PC Construction was the only bidder on the rebid. Staff and PC Construction performed value-engineering discussions after bids opened and were able to lower the amount by about $188,000 from the initial submission. Staff recommended awarding the project to PC Construction in the amount of $8,094,300. The work includes replacement of internal filter components (not structural concrete tanks) and related valve and actuator replacements plus pipe-gallery painting and miscellaneous repairs. The committee approved the award by voice vote.
Staff characterized the filter work as a full replacement of the filter internals while retaining structural concrete tanks.