Council approves $32,144 change order and small budget amendments for new fire apparatus bay
Summary
The council approved a contract change order totaling $32,144 for motorized doors and a concrete-floor sealer for the new fire apparatus bay and authorized small budget transfers to cover the work.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The City Council on June 18 approved a change order to the construction contract for the city's apparatus bay (fire station apparatus bay phase 1) that adds motorized doors and a concrete-floor sealer intended to protect heavy truck traffic and prolong the slab's useful life.
Assistant engineer Alex Ramos told the council the change order contains two principal elements: (1) motorized overhead doors to speed apparatus deployment and reduce manual handling; and (2) a commercial flooring product (a concrete surface coating) to protect the slab from heat and wear from large ladder-truck tires. Ramos said the existing building predates contemporary electrical and building-code assumptions, so some electrical work and component selection required late-stage adjustment, making the change order necessary.
Staff recommended and council approved a change order in the amount of $32,144 and two related budget amendments to the fire-impact fee capital improvements line for FY24–25 ($15,000) and FY25–26 ($17,144). Councilmembers said protecting the new facility now reduces long-term maintenance costs.
Formal action: council approved the change order and the fiscal adjustments by voice vote.