Nettle Creek micro-hydro expected to start next week; town staff flags geothermal opportunities with Holy Cross Energy
Summary
Town staff reported new equipment delivery and imminent startup for a micro-hydro project at Nettle Creek and raised potential future connections between wastewater, geothermal opportunities and Holy Cross Energy planning.
Town staff reported that components for the Nettle Creek micro-hydro project have arrived and electricians were completing installation ahead of a planned startup next week.
Scott, a town utilities staff member, said a custom control panel and other control hardware were delivered and electricians were on site to finish installation. Scott said the system is a roughly 45-kilowatt generator, with variable flow expected…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat