Frangill Road improvements: Work zones advancing; zone 3 forecasted to finish in August
Summary
Contractor Acosta has completed work zone 1 and is finalizing zone 2, the town reported May 21; zone 3 drainage installation is underway and the town expects the full stretch to be open to traffic by late August, weather permitting.
Get email alerts on the Infrastructure Streets topic
No spam. Unsubscribe anytime.
Town project staff and the design consultant updated the council on Frangill Road construction on May 21, describing completed work zones, current activity, public outreach, and a projected completion window.
What’s happened and what’s next
- Work Zone 1 (Frangill from 180th to Sterling Drive) is complete and open to the public. - Work Zone 2 is nearing finalization; some rain delays were reported and the contractor is addressing final streetscape elements, signage and markings before opening that segment. - Work Zone 3 construction has started; crews are installing drainage near 192nd Drive. The project team said they will update the public with a flyer explaining changes to traffic control once Zone 2 opens. The town estimated Zone 3 completion around Aug. 25 but noted the rainy season could cause further delays.
Public involvement
Public‑engagement staff said resident feedback has been generally positive, noting that residents in later zones are eager to see the same improvements completed in their streets. The project team holds biweekly progress meetings with the contractor, town staff, and the engineer of record.
Speakers
- Stefano (Kimley‑Horn project representative) (consultant) - Janet (public involvement lead) (consultant) - Savannah (town staff) (government)
Clarifying details
- Work zone three projected completion: August 2025 (town estimate, rain‑dependent). - Public outreach: flyers and resident coordination to continue; biweekly project meetings ongoing.
Provenance
- topicintro: {"block_id":"5987.31","local_start":0,"local_end":80,"evidence_excerpt":"Jumping into the Frangill Road update... This is our May update on the Frangill Road project."} - topfinish: {"block_id":"6214.66","local_start":0,"local_end":40,"evidence_excerpt":"K. Thank you, Savannah...August '3 should be completed."}
sections:{"lede":"Contractor work on Frangill Road continues in three staged work zones, with zone 1 open and work zone 3 under construction; town staff estimates zone 3 will be finished by late August, weather permitting.","nut_graf":"Project staff said drainage installation is underway in zone 3 and the contractor is finishing streetscape items in zone 2; the town will distribute a public flyer once the traffic control plan for zone 3 is finalized.","ending":"Town staff will continue biweekly progress meetings with the contractor and update residents through the public‑involvement team as each zone is completed."},