Legacy Park earthwork advancing; import/export totals and timeline reported

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Stantec owner’s representative reported soil export/import totals and percent complete for Legacy Park and said phase‑one earthwork is underway while vertical design for phase two continues; final design and permit submission anticipated in summer with construction and closeout spanning into late 2025.

Emma Jones, the town’s owner’s representative from Stantec, updated the Town Council on Legacy Park construction progress on May 21, reporting excavation and import tonnages, staging milestones, and a schedule for design and permitting.

Key progress and figures

Jones said the original site contracts called for approximately 98,546 tons of exported soil and 194,229 tons of imported material. To date the town has exported 7,298 tons (about 958 truckloads) and imported 55,829 tons (about 2,521 truckloads), representing roughly 8% of the export work and 29% of the import work.

Schedule and next steps

Phase 1 (site clearing and earthwork) began with tree clearing and grubbing in April and installation of construction entrances and a truck‑wash station. Jones said soil excavation started in…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans