VMNH to reallocate reserve and project funds to complete Waynesboro detailed design; pavilion installation and exhibits nearing completion
Summary
Museum leaders proposed reallocating $150,000 from Waynesboro and other internal accounts to fund detailed design work needed to pursue state capital construction funding; the Gina Adams Education Pavilion installation and a Hall of Ancient Life sculpture are expected to be finished soon.
Staff told the executive committee that they plan to reallocate existing funds to complete the detailed design for the Waynesboro project and position the museum to apply for the state capital construction pool.
Staff said the construction manager (JMU) will commission independent peer reviews (value-engineering study and cost estimate) and that staff will submit the full study to DEB as part of the capital request. Because prior appropriations did…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat