Justice Center annex nears completion; county flags major foundation repairs and fairgrounds activity
Summary
Facilities director reported that the Justice Center annex is nearing substantial completion in two weeks; inspection work identified foundation issues at the jail and Navasota annex with repair cost estimates; fairgrounds hosted large crowds during county fair and staff are managing high use.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
Rodney Floyd, Grimes County facilities director, told the Commissioners Court on June 11 that the Justice Center annex work is progressing and that substantial completion is expected within two weeks, with furniture staging and IT trim‑out planned. Floyd also presented a foundation assessment that identified two structures (the jail entrance area and the Navasota annex) with pilings and repair needs; the Navasota repair estimate began at about $337,000 and Floyd warned the final bill could increase by up to 25 percent as additional work is discovered.
Floyd said contractors are finishing ceiling tiles, millwork and the HVAC trim and that DPS move‑in is likely in the coming days. He described ongoing site‑signage and building readiness work associated with the new annex and said staff are coordinating moves and furniture disposition for existing leased spaces.
On the fairgrounds, Floyd reported very high attendance during the week: nightly crowds of an estimated 750+, a Queen’s crowning with roughly 1,200 attendees at one event, heavy camper use and only minor facility incidents that the maintenance staff and sheriff’s diversion crew promptly addressed. He said cleaning and post‑event restoration are underway and estimated the facility will be fully reconditioned by mid‑ to late next week.
Why it matters: The annex move affects several county operations (DPS, adult probation) and the foundation repairs represent a significant unplanned capital need. Floyd's estimate for one foundation repair is substantial and may require future budget decisions.
What’s next: Staff will present formal repair options and costs for commissioner consideration. Court members discussed lease timing for adult probation’s existing space and possible auction of county furniture to streamline moves.