South Canadian improvements 65% complete; Trust aims to energize electrical loop next
Summary
Trust staff reported the South Canadian Improvements Project is roughly two-thirds complete by work and finance, with substantial completion targeted next February and final completion in February 2027.
At the June 3 Oklahoma City Water Utilities Trust meeting, project staff provided a quarterly update on the South Canadian Improvements Project, the Trust’s largest current wastewater treatment-plant modernization effort.
Joy Cote, the project presenter identified in the record, said STV (formerly CPMY) is the project engineer and Crossland Heavy Contractors is the prime contractor. Cote said the project’s construction cost after the latest change order is just over $190,000,000, with payments of…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat