Keizer awards 2025 pavement resurfacing contract to K & L Industries; work to cover about 1.7 miles

3636308 · June 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The city awarded the annual pavement resurfacing contract to K & L Industries after K & L submitted the lowest responsive bid; the project includes about 1.7 miles of streets and curb-ramp upgrades where needed.

Keizer City Council authorized the city manager on June 2 to enter into an agreement with K & L Industries Inc. for the 2025 pavement resurfacing project.

Scope and procurement: the annual resurfacing covers approximately 1.7 miles of streets including Shady Lane, Evans Avenue North, Mambin Drive North, Burgundy Avenue and Court, Shadowwood Loop, Amy Lane, Leprechaun Court, Blarney Stone Court and River Rock Drive NE. The project includes resurfacing and replacement of Americans with Disabilities Act (ADA) curb ramps where they do not meet current standards; on a few streets the ramps already meet current standards and will not need replacement.

Bids were received through a formal competitive process; the lowest responsive bid to K & L Industries was substantially lower than the engineer's upper estimates and will allow the work to proceed during the summer paving season.

Why it matters: pavement resurfacing affects ride quality, drainage and long-term street preservation. Staff said additional funding would increase the number of lane miles the city can maintain each year and urged steady investment to avoid accelerated deterioration.

Key details - Extent: ~1.7 miles of city streets. - Contractor: K & L Industries Inc., lowest responsive bidder. - ADA: Project includes replacement of curb ramps on streets where ramps do not meet current standards.

The council approved the contract so crews can begin paving later this summer.