Staff identified several entitlement steps and technical constraints for the proposed 33‑lot Villas at Winding Creek subdivision, including minimum-lot-size shortfalls on some parcels, potential FEMA/floodplain processes, cul‑de‑sac radius increases, and dedication/easement needs; staff will issue a consolidated comment letter in about 2–3 weeks.
Get email alerts on the Subdivision And Infrastructure topic
No spam. Unsubscribe anytime.
Porterville staff reviewed a tentative subdivision map for the proposed Villas at Winding Creek, a 33‑lot single‑family subdivision at the northwest corner of the Poplar Ditch and South Indiana Street, and identified substantive entitlement and technical requirements for the applicant.
Planning staff said the project, proposed in a Low Density Residential zone, requires a tentative map application and related fees. Staff identified several lots that do not meet the RS‑zone minimum lot area of 6,000 square feet and said the applicant could pursue a spot-lot subdivision or request variances through a single conditional use permit. The tentative map and any conditional‑use requests will require public hearing notice and discretionary approval; the final map must follow approval under section 405 of the development ordinance.
Engineering staff flagged multiple infrastructure items: extend dedication and easements south of Myrtle Avenue to accommodate an extended culvert over the Poplar Ditch; ensure lots in Flood Zone A are either raised or processed through FEMA procedures to remove building limits from the flood area; maintain a looped hydrant system where required; and provide a minimum cul‑de‑sac diameter of 96 feet (48‑foot radius) to meet fire‑code expectations. Staff also asked that a groundwater recharge line / storm/storm-recharge easement be reserved, likely within Wisconsin Street right‑of‑way, and noted required parkway trees and street-lighting improvements.
Fire staff reiterated residential hydrant spacing (no greater than 500 feet) and that no structure be more than 400 feet from a hydrant, and said two points of entry must be maintained.
Public works and streets staff asked for signage and stop-bar/legend installation where Myrtle meets Indiana, and police had no comments. Planning and engineering said fees, environmental review (CEQA-equivalent), and a public hearing are required; planning staff quoted the tentative subdivision map fee and per-lot fee for processing.
Staff told applicants they will receive consolidated departmental comments in about two to three weeks. The primary outstanding items for the applicant to address before the tentative map can move forward are minimum-lot-size adjustments (or a CUP to vary standards), floodplain/FEMA issues for lots in Flood Zone A, right‑of‑way/easement extensions for drainage and recharge infrastructure, cul‑de‑sac geometry changes, and parkway/street improvement designs.