North Ogden completes phase 1 of 400 East widening; project included retaining walls, bike lanes and a signalized intersection
Summary
Eric Caspersen, North Ogden City engineer, described the recently completed phase 1 of the 400 East/450 East widening project, its design changes, funding, costs and construction challenges, and said phase 2 is planned to start next spring.
City Engineer Eric Caspersen presented North Ogden’s 400 East (450 East) widening project at the May 28 TransCom technical advisory meeting, reviewing design decisions, construction challenges, funding and next steps.
Caspersen said the corridor widening began in 2019 and was completed in a phased approach. Phase 1 widened the roadway between about 2600 North (Washington Boulevard North) and roughly 2975 North. The original right of way was about 102 feet; the project reduced that to about 92 feet to help lower costs. The corridor previously had two 11.5‑foot travel lanes in each direction and a 15‑foot center…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat