NUPEC construction nearing completion; windows to be retested, furniture deliveries set for July

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Construction administrators reported the NUPEC school building is about seven weeks from substantial completion, with FF&E and technology deliveries starting July 1. Vendor Pella is remediating window sealant issues and will run further tests; the project team said inspections so far haven’t found deficiencies.

At a meeting, construction staff and project administrators updated participants that the new NUPEC school building is roughly seven weeks from "substantial completion," with furniture, fixtures and equipment (FF&E) and technology deliveries beginning the first week of July.

Chris, the construction administrator, said the contractor is winding down major work and "we're about 7 weeks away from substantial completion," while crews continue finish work inside and on site. He told the meeting the site is maintaining "100 to 120 people on-site on a daily basis" doing tasks from site work to finish paint and tile.

The update covered three main areas: construction progress, a window-testing and remediation effort, and the FF&E/technology delivery and move-in timeline. The construction update emphasized interior finish work (flooring, ceiling grid, lockers and gym floor installation),…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans