Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Transportation Projects topic
No spam. Unsubscribe anytime.
Council delays major redesign of Rogers Road–Wesley Chapel intersection after staff recommendation
Summary
After a public outreach process and engineering alternatives analysis, staff recommended delaying action on a multi-million-dollar redesign of the Rogers Road–Wesley Chapel intersection; council voted unanimously to take no immediate action and revisit the project later.
Get email alerts on the Transportation Projects topic
No spam. Unsubscribe anytime.
The town council declined to select a design alternative for the Rogers Road–Wesley Chapel intersection and instead voted to defer action until later, following a consultant outreach and alternatives analysis.
Staff described three design alternatives that had been presented to nearby residents in public outreach: (1) a split intersection with two closely coordinated signals; (2) a quadrant solution that retains the existing intersection and adds three coordinated signals; and (3) a lower-cost option that keeps the intersection in place while adding turn lanes and retiming the signal. Public survey responses favored the lower-cost option, but staff noted that the low-cost option would provide the least long-term reduction in queue lengths and crash predictions for a 2050 design year.
Todd Barber, SWAC chair and council member, said the staff recommendation was that the town not select a design at this time, noting that the project would likely not start until after other projects and into the 2030s; the consultant had provided cost estimates ranging from about $3.9–11 million depending on the alternative and time-based escalation. "We really wouldn't... move forward with this project anyway till after 2030. So why don't we just sit on it for a while," Barber said.
Council voted unanimously on a motion “not to do anything” at this time and asked staff to retain the study's data for a future revisit when project scheduling and funding better align with the town's capital program.
Ending: Council did not authorize design or funding and will revisit the intersection when priorities and funding permit.