ATP outlines upcoming procurements, to issue light‑rail vehicle RFI by month end; single‑step RFP planned for up to 30 cars

3439997 · May 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

ATP staff told the board they will publish RFQs/RFIs this summer for the civil/rail/stations progressive design‑build, the operations and maintenance facility and light rail vehicles, and they described a single‑step fixed‑price vehicle procurement for up to 30 cars with long‑term parts and technical support provisions.

ATP staff presented a timetable and technical approach for three major procurements this year and described details for the light rail vehicle (LRV) contract.

Brad Cummings, ATP senior vice president for procurement, said ATP will issue an RFQ for the civil/rail/stations progressive design‑build procurement in early June. The operations and maintenance facility (OMF) procurement had an April RFI with responses due May 28; ATP plans a Connect & Build industry event on May 29 (doors 9:00 a.m., program roughly 9:30 a.m. to 1:00 p.m.) to help prime contractors and subcontractors meet and form teams. In early June ATP will also publish a vehicle RFI so manufacturers can review draft vehicle specifications and the contract.

Lindsay Wood, ATP’s design and construction lead, told the board the LRV procurement will be a single‑step request for proposals (RFP) for a fixed‑price contract for up to 30 vehicles. Wood said the contract will include not only the vehicles but “the necessary equipment that you’ll need in order to kind of maintain the fleet, not only for the short term but the long term.” Matt Bertrand, ATP’s light rail vehicles manager, added that ATP is seeking a vehicle supplier that can provide long‑term technical support and spare parts access: “vehicles are sometimes considered moving data centers,” he said, arguing for robust parts and technical‑support provisions in the contract.

Staff described the vehicle contract as including a short base period and longer parts/support options; in the meeting transcript staff said the procurement will include “a 6 month base with 2 additional 5 year options.” ATP staff said that structure is intended to improve protections against obsolescence, secure long‑term parts access and align manufacturer responsibilities with ATP’s OMF and civil design teams.

Cummings described the agency’s outreach and procurement approach as intentionally iterative: ATP published RFIs and hosted “Connect and Build” events so industry can comment on draft documents and prime/sub teams can form. Staff reported survey results from a previous Connect & Build: 89 attendees representing 15 firms, including 49 registered certified DBE firms; the majority of attendees rated the event “excellent” or “good.”

On Buy America and DBE compliance, staff said vehicle manufacturers must submit DBE goals to the Federal Transit Administration (FTA) for approval; ATP verifies the manufacturer’s FTA‑approved DBE commitments rather than setting a separate subcontracting process for vehicle manufacturers. Brad Cummings said ATP expects to conduct pre‑award Buy America audits and noted a recent increase in domestic content requirements: “in the last few years there has been a step up in the requirements ... where it’s gone from 60% to 70%,” he said.

Staff estimated the vehicle RFP will be published in the fall with an award expected in 2026. ATP also emphasized coordination across contracts — vehicles, civil/systems progressive design build and the OMF — so vehicle builders, PDB contractors and the OMF contractor can coordinate design interfaces and testing schedules.

Why it matters: The procurement schedule and the vehicle contract terms set the technical and commercial framework for vehicle availability, testing and long‑term maintainability; ATP staff emphasized outreach and early industry input to reduce procurement risk and encourage DBE participation.