Commission briefed on emergency coastal permit and funding to replace Tenth Street stairs this summer

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said the city will replace the Tenth Street beach stairs “like-for-like” with reclaimed redwood under an emergency coastal development permit, using $59,999 in available funds plus a $15,000 donation from Carmel Cares; work is expected in July.

Staff told the commission the city will proceed with an emergency, like-for-like replacement of the Tenth Street beach stairs and that the work is scheduled for summer.

The city is pursuing an emergency coastal development permit that allows a like-for-like replacement; staff said reclaimed redwood will be used and that some existing wood on site can be reused. Staff described the procurement path and said the project falls under CHIP authority at the $59,999 threshold, enabling a streamlined contract and permitting approach.

City staff said Carmel Cares donated $15,000 toward the work, and that internal staff will perform demolition while a contractor completes the replacement. Staff said they are aiming for July construction but noted permitting checks and careful administrative steps must be finished before work begins.

Commissioners asked about signage during temporary closures; staff said they will post updates and consider laminated notices indicating work is in progress and that access will be restored as soon as possible.

Staff also reported other beach-related near-term work: temporary repairs to stairs elsewhere, fencing around Devendorf Park to protect the public during work, and a review of the Fourth Avenue outfall as part of longer-term design work.