Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Subdivision Variance Superfund Adjacency topic
No spam. Unsubscribe anytime.
Commission approves Beamer Business Complex variance; site adjacent to EPA Superfund containment
Summary
The commission granted a variance to avoid dedicating right-of-way to a 30-foot paper street for the Beamer Business Complex site, noting the nearby former refinery is a long-standing EPA Superfund containment and the paper street terminates half a mile south.
Get email alerts on the Subdivision Variance Superfund Adjacency topic
No spam. Unsubscribe anytime.
The Planning Commission approved a variance for the Beamer Business Complex (item 103) that allows the applicant to avoid widening or dedicating a corner cutback to a 30-foot paper street abutting the western boundary of the site.
Jeff Butler presented the item and described the site as located south of Beltway 8 and west of the Gulf Freeway in the Harris County extraterritorial jurisdiction. Butler said the site sits immediately north of a former refinery designated an EPA Superfund site since the 1980s and that the containment facility is unlikely to be developed for the foreseeable future.
Staff supported the variance, noting that the paper street terminates about a half mile south and abutting owners previously received variances to terminate and not widen the street. Given the site constraints and surrounding industrial context, staff concluded a 30-foot right-of-way dedication and corner cutback would be impractical and recommended approval of the variance and plat subject to CPC conditions.
The commission approved the staff recommendation by voice vote; no advanced written comments were received. The approval allows the developer to proceed without the 30-foot dedication or corner cutback tied to the paper street, consistent with prior variances granted in the corridor.
Butler noted the Superfund containment and unusual site history during his presentation; the commission did not attach additional conditions beyond the CPC form conditions as presented in staff reports.