Assembly hears request for change order to address Main Elementary roof deterioration

3661751 · June 4, 2025

Summary

Staff requested a change order of approximately $64,560 to complete professional services and planning for replacing the deteriorated shingle roof at Main Elementary; staff recommended using 50-year architectural asphalt shingles rather than metal in the marine environment.

Staff briefed the assembly on a requested contract change order for the Main Elementary School roof replacement, citing damage from pressure washing and long-term deterioration of wooden shingles.

The presentation described field observations that showed moss damage and localized soft areas. Staff recommended designing a replacement roof with architectural asphalt shingles (50-year rated product) rather than metal roofing because saltwater exposure and fastener corrosion have caused problems on other local metal roofs. The requested change order of about $64,560 covers design and construction-administration services so the project can be put out to bid with a full package.

Assemblymembers asked about warranty and material choices. Staff said certain metal systems and high-end manufacturers can perform in marine environments, but installation details and exposed cut edges and fasteners create corrosion risks; staff favored a long-life asphalt shingle as the most reliable choice for the island environment. Staff also said the contractor that performed a prior pressure-washing job is no longer local and that the earlier approach (water blasting cedar shingles) accelerated roof degradation.

Why it matters: school-roof replacement is a capital-maintenance item affecting facility condition, long-term maintenance costs and safety; choosing a durable material appropriate to seaside exposure is important to minimize future repairs.

Ending: The assembly asked staff to finalize design documents and include construction administration in the change order so the borough can proceed to bid and, if necessary, phase work according to budget availability.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source