Milpitas council adopts five‑year capital improvement program totaling $246 million

3650551 · June 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The City Council approved a five‑year Capital Improvement Program (CIP) covering 147 projects and a FY2025‑26 CIP budget of $38.7 million, and authorized a $50,000 appropriation for an environmental site assessment at 230 North Main Street.

The Milpitas City Council on June 3 adopted the city’s FY 2026–2030 Capital Improvement Program (CIP), approving a five‑year plan that includes 147 projects and an estimated budget of $246 million.

Liehak, public works division manager, presented the CIP and a timeline of outreach and approvals. Staff recommended funding 38 projects in FY 2025–26 with a total FY25‑26 CIP appropriation of approximately $38.7 million. The five‑year needs assessment in the presentation identified roughly $657 million in infrastructure needs, including $242 million for replacement and repair of existing infrastructure and $415 million for new infrastructure needs.

Staff highlighted completed projects and near‑term construction: park and playground rehabilitation, an updated council chambers audio‑visual system, multiple resurfacing projects, a Dempsey Road water line replacement (construction under way), fabrication of a modular building for Fire Station No. 1, and the McCandless well project. The presentation also proposed $1.7 million from the Park Fund to renovate an aging playground (presentation named the project "Singapore playground innovation project") and recommended $100,000 for temporary improvements and sound‑mitigation measures at Hall Park pickleball courts.

The council heard public comment supporting the CIP and the recommended appropriation for a phase‑2 environmental site assessment at 230 North Main Street; staff asked the council to appropriate $50,000 from Midtown Park Fund to amend a professional services agreement for that work.

Councilmember Chua moved to adopt the CIP and the recommended appropriation; Councilmember Lian seconded. The motion carried unanimously.

Staff will proceed with the projects funded in the adopted CIP and the proposed amendments to professional services agreements; capital project schedules and funding sources will be reported through the regular project and budget monitoring process.