Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Landfill Management topic

No spam. Unsubscribe anytime.

Commissioners authorize $8,642 Terracon invoice for landfill vertical-expansion design and bid prep

3636499 · June 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Linn County approved an $8,642 invoice from Terracon to finalize perimeter berm and channel design drawings, update the waste-capacity review, and begin a bid package for vertical expansion of the county landfill. The work will be paid from ARPA funds and public works will return with a proposal on adjacent-lot expansion.

Linn County commissioners on June 2 authorized payment of an $8,642 invoice from Terracon for final design and bid-preparation work on the county landfill's vertical expansion. Public Works reported that the consultant's invoice covered perimeter berm and channel design drawings, an updated waste-capacity review, minor permit modifications for county approval, travel time and coordination activities including staking and site meetings.

Public Works staff said Terracon set benchmarks and a grid of stake points that identify how much fill can be placed at specific locations; commissioners were told the stakes will help ensure vertical expansion occurs within regulatory and engineering limits. The consultant also recommended revisiting an adjacent-lot expansion; commissioners directed staff to ask Terracon for a proposal to study that option and to bring back a bid package and timeline.

Commissioners approved the invoice to be paid from ARPA funds. The board asked staff to return when Terracon has a proposed scope and schedule for the adjacent-lot option so the county can decide whether to pursue that parallel track.

Quotes "This invoice that I have is for $8,642," Public Works said during the meeting in describing Terracon's work and the items covered.

Context and next steps Public Works will follow up with Terracon to assemble a full bid package (including GPS requirements for contractors) and to seek a proposal for expanding onto the adjacent lot. Staff estimated the original vertical-expansion design had a rough expected life of 10 to 20 years depending on incoming waste characteristics; commissioners discussed starting parallel work earlier to avoid delays if demand accelerates.

The payment was approved during the meeting and recorded in the minutes; the county intends to use ARPA funds to cover the cost.