ODOT declares emergency, awards contract to repair Roosevelt Bridge causeway at Lake Texoma
Summary
The Oklahoma Department of Transportation closed the Roosevelt Bridge causeway on U.S. 70 after storm-related scour and erosion, approved an emergency contract to repair the causeway and announced an accelerated replacement plan funded in part by a large grant.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
The Oklahoma Department of Transportation declared an emergency and awarded an emergency contract to repair the causeway at the east end of the Roosevelt Bridge over Lake Texoma, after record April–May rainfall and high winds caused scour and erosion that compromised the causeway and forced a closure on U.S. 70.
ODOT Director Tim Gatz said the causeway damage “necessitating closure of the Roosevelt Bridal to protect the public,” and that the closure required an approximately 35-mile detour for residents, visitors and emergency services serving Marshall and Bryan counties. Sean Davis, who presented the item to the commission, told commissioners the closure “has compromised emergency services and negatively impacted the economic viability of the area.”
Why it matters: U.S. 70 is a primary east–west route across southern Oklahoma. The closure increased travel times, complicated access for emergency responders and local commerce, and made rapid repair a priority for the department.
What the commission approved: Director Gatz had declared an emergency under state authority that allows the department to issue emergency contracts up to $750,000. Commissioners subsequently approved an emergency contract awarded as call order 001 in the May emergency bid opening that exceeds the director’s statutory emergency-award limit; staff described the related contract amount as $5,600,000 and the motion to award passed at the June meeting. ODOT staff identified BridgeCo as the successful contractor; the department said BridgeCo will proceed with repairs and that the agency will continue 24/7 monitoring during construction.
Funding and next steps: Director Gatz said the department has “all of the financial wherewithal” to accelerate a full replacement project, including about a $125 million grant that will help fund a replacement bridge. ODOT said it will push to present the larger replacement contract for commission consideration in short order, with an optimistic target of early calendar-year 2026 for funding and contract award. Temporary traffic control measures have been put in place and district staff shifted traffic to the north side of the causeway to open two lanes while repairs proceed.
What remains uncertain: The emergency declaration facilitated immediate emergency work and a bid letting; ODOT staff clarified that the director’s $750,000 emergency authority initiated traffic and assessment steps, while the full repair contract exceeded that limit and required commission award. The commission and staff said they will continue local engagement and public advisories through construction.
Ending: Commissioners thanked district crews and ODOT staff for rapid assessment and response. Director Gatz said the department will keep the public informed through traffic advisories as repair and replacement work proceeds.