Justice Center construction at about 42% complete; county updates ARPA-funded projects

3626053 · June 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County Engineer John Hernandez told commissioners the new Justice Center is roughly 42% complete, with mechanical, electrical and plumbing work driving schedule; ARPA-funded projects — a bridal shelter, juvenile detention extension and county fiber-optic build — were also updated.

County Engineer John Hernandez told the San Patricio County Commissioner's Court that the Justice Center construction is approximately 42% complete and that the month’s payout to the contractor was about $2.2 million.

Hernandez said interior work — in particular mechanical, electrical and plumbing (MEP) systems — is the current critical path for the project and that work on those systems will likely keep the schedule active through July and possibly into August. He said the county approved a change order to proceed with design of a fire-suppression water storage tank and that further coordination with the architect and urban engineering is underway.

Hernandez described elements of ongoing work, including cinder-block interior units and steel reinforcement that will be grouted as the project progresses. He told the court the project is moving from the first-floor MEP work toward the second and third floors as interior framing and rooftop mechanical pads are installed.

Hernandez also updated the court on ARPA-funded projects: a bridal shelter project is about 15% complete and waiting on a water tap from Rincon Water Supply; a juvenile detention center extension is approximately 37% complete and will have grout pours and laboratory testing for concrete quality in the coming days; and the county’s fiber-optic backbone build is about 19% complete, with a planned August completion for the fiber route.

Steven (county staff) provided a routing diagram for the fiber project showing a path from the Emergency Operations Center through the sheriff’s department, courthouse, justice center, annex and to the radio tower; he reported no current schedule issues related to weather or the community.

Commissioners praised visible progress and asked technical questions about systems, the storage tank schedule and adjacent site work; no change to contract awards was reported during the update.