Public works OKs rectangular rapid-flashing beacons at Cherry Street; WellStar to pay half
Summary
Public Works recommended and the committee approved installation of two RRFB pedestrian beacons at a Cherry Street mid-block crossing; WellStar Kennestone pledged to cover half of the estimated $115,000 cost ($57,500).
Get email alerts on the Pedestrian Safety topic
No spam. Unsubscribe anytime.
Public Works staff presented a proposal to install two rectangular rapid-flashing beacons (RRFBs), related electrical work, signage and striping for a mid-block crossing on Cherry Street between Church and Cherokee Street, and the committee approved the concept.
Staff estimated the entire installation at approximately $115,000, and WellStar Kennestone Regional Medical Center provided a letter committing to pay half the cost ($57,500). Public Works said the RRFB would be timed to coordinate with adjacent traffic signals to avoid safety conflicts.
Committee action: Committee members moved and seconded the public-works recommendation and recorded approval; staff said the project would be funded from safety allocations with WellStar's contribution reducing the city's net cost.
Why it matters: The crossing serves a pedestrian corridor and the RRFBs are intended to improve safety and visibility for people crossing Cherry Street near downtown. The project will include electrical power, signage, and pavement markings.
Next steps: Staff will proceed with design and procurement and coordinate the schedule with WellStar and utilities; the city will finalize the funding arrangement and begin installation per the usual procurement timeline.