County told Cat generator ordered for emergency management won't arrive until August; commissioners discuss rental and interim options
Summary
Staff reported a Cat generator ordered for the emergency management building has a multi‑month lead time (22–25 weeks after final submittal) pushing delivery to August; commissioners discussed rental options, transfer‑switch needs and short‑term workarounds.
Wagoner County staff told commissioners on May 20 that a Caterpillar generator ordered for the emergency management facility has a long manufacturer lead time and — as currently contracted — would not be delivered until August after submittals and approval steps, prompting questions about interim power options.
The county’s procurement follow‑up showed a 22‑ to 25‑week lead time once submittals and approvals are complete. Staff said the original…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat