Commission authorizes bids for Weibo Drive sewer and Jersey Avenue drainage projects
Summary
The Huron City Commission authorized bid solicitation for a Weibo Drive sanitary sewer replacement and Jersey Avenue drainage improvements, setting a June 24 bid opening and approving estimated budgets of $300,000 and $360,000 respectively.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Huron City Commission voted to authorize bid solicitations and set a June 24 bid opening for two public-works projects: a sanitary sewer replacement on Weibo Drive and drainage improvements on Jersey Avenue.
City Engineer Brett Runge told commissioners the Weibo Drive section contains a deteriorated 15-inch concrete sanitary sewer that has been collapsing and resisting cleaning; contractors stopped cleaning during inspection because interior pipe segments were failing. “It’s in dire need,” Runge said. The city budgeted $300,000 for the replacement and recommended proceeding to bid.
Runge and staff also presented plans for Jersey Avenue, a site north of the railroad bridge where recurring storm events have overtopped the road and eroded the adjacent bank along the James River. Infrastructure Design Group assisted on the plans; staff said the project will replace existing 48-inch corrugated-metal culverts with concrete structures and add bank stabilization. The estimated cost is $360,000.
Runge explained the change in approach: instead of a “Texas crossing” where water runs over a reinforced concrete section and the culverts remain, the city will replace the corrugated culverts because leaving them would limit the new concrete design’s 50-year expected life. He also said surveys showed a deep washout beyond the culvert outfalls that requires bank stabilization.
Both motions passed on roll-call votes. The council did not specify the motion makers on the transcript; the roll-call recorded the following votes for each project: Smith — Aye; Clute — Aye; Craig — Aye; Harvey — Aye; Mayor Robich — Aye.
Next steps: staff were authorized to issue addenda as needed and to accept bids at the June 24 opening. No contract awards were made at the meeting; award decisions will follow the bid-opening process.
Votes at a glance - Weibo Drive sanitary sewer replacement (project 2025-04): Authorized solicitation; estimated budget $300,000; bid opening set for June 24. Vote: unanimous (Smith, Clute, Craig, Harvey, Mayor Robich: Aye). - Jersey Avenue drainage improvements (project 2025-24): Authorized solicitation; estimated budget $360,000; bid opening set for June 24. Vote: unanimous (Smith, Clute, Craig, Harvey, Mayor Robich: Aye).
Background: Runge said the Weibo Drive pipe carries gravity flow for areas north of Highway 14 and serves multiple lift stations; the Jersey Avenue site has failed repeatedly in major rain events. The commission instructed staff to move forward to the bidding stage.