The Winnebago County Board of Supervisors held public hearings and approved an annexation report and a reclassification (assessment) report for Drainage District (DD) 78, adding eight parcels and adjusting benefit classifications and assessment factors; officials said affected landowners will be notified of estimated costs.
Get email alerts on the Drainage Districts topic
No spam. Unsubscribe anytime.
The Winnebago County Board of Supervisors on Tuesday opened public hearings on an annexation report and a reclassification report for Drainage District 78 and approved both after discussion and no public objections were recorded. The board voted by voice to adopt the annexation and later the reclassification report; the chair declared both motions passed.
Consultant Colin (presenter) explained the annexation map and the district history, saying the district was established in 1917 and later modified by a 1979 petition that created an open ditch on the south side of Highway 9. The annexation proposal would add eight parcels totaling about 74.6 acres to the district, and most of that acreage (roughly 60 acres) involves lands tied to the ditch and the tile system.
The consultant said the annexation map shows lands in red proposed for inclusion. He explained that two small laterals listed historically (laterals 4 and 5) could not be located on modern records and therefore were not included. He said the maps include elevation and watershed visuals to show how water flows to district facilities and to justify which parcels benefit from the district.
On the reclassification, the consultant said staff produced two assessment schedules (one for the open ditch, one for tile/laterals) and drafted “dollars maps” showing estimated parcel assessments based on a $10,000 levy example. He described the methodology used to compute benefit and classification: acres in the parcel that drain to the facility, soil type (wetter soils count for greater benefit), distance to the district facility (closer parcels receive more benefit), land use type (pavement and roads generate higher runoff), and an adjustment factor used to make allocations equitable.
The board discussed adjustment factors applied to specific parcels. A wooded tract planted in the 1980s under a conservation program received an adjustment factor of 0.8 because it is unlikely to return to row-crop agriculture. A separate, permanently protected wetland area at the north end of the district received an adjustment factor of 0.5 to reflect its permanent easement and limited benefit from the drainage system. The consultant said those adjustments reduce those parcels’ share of future maintenance bills, though the math spreads costs across the district.
Colin reported he had interviewed affected landowners, including Carl Wagner and the Charleston family, and said the parties contacted said they understood the changes (Wagner will see his assessment increase because more acres are included but received a partial reduction for permanent wetland). The consulting presentation and maps will be available to affected landowners online, and the county will send letters with estimated costs; staff said they intended to send those notices at the end of the month.
Formal actions: the board opened and closed the public hearings for both the annexation and the reclassification and voted to approve the DD 78 annexation report and the DD 78 reclassification report. The motions were adopted by voice vote with no recorded opposition.
Why it matters: Annexation brings additional parcels under the legal authority of DD 78 for maintenance and assessment; reclassification updates the county’s assessment schedule so future maintenance bills are proportionally allocated to parcels that benefit from the drainage facilities.
The board directed staff to send the annexation report and reclassification materials and maps to affected landowners and to issue estimated bills once final numbers are computed. The consultant said the annexation added a relatively small number of parcels and acres but clarified the legal status of the open ditch constructed in 1979 as a district facility, which allows future maintenance to proceed under the drainage district authority.
The board concluded the matter after approving both reports and confirming procedures for notifying landowners.