Board approves Mammoth design agreement; board discusses $3.2M estimate for track and field project

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The district approved a design agreement with Mammoth for a potential track and field renovation. Staff presented a $96,000 design fee, optional $24,000 drainage design and an early rough estimate of about $3.2 million for a full project including turf, bleachers and lighting.

Spearfish School District 40-2 on June 9 approved a design agreement with Mammoth for a proposed track and field renovation and discussed preliminary cost estimates and financing projections.

The design services exhibit presented to the board listed a $96,000 fee for design services; an optional drainage design for the east-side area between the track and parking lot was listed at $24,000. Staff recommended approving both Exhibit A (design services) and Exhibit B (construction-phase services, should the district choose to proceed).

Staff and the facility committee explained that a construction estimate for the combined scope (track, field, drainage, bleachers, press box and lighting) was roughly $3.2 million in the materials presented. That estimate included a track-only design estimate of about $1.4 million (including sidewalk and fencing); an additional roughly $1 million for installing artificial turf and associated drainage for the field; a bleacher and press-box package estimated in the materials at roughly three-quarters of a million; and sports lighting as an alternate of about $310,000. Staff emphasized the figures were estimates and that the facility committee would refine scope and present a guaranteed maximum price if the board later authorized construction.

Staff noted the district participates in a cooperative purchasing agreement that could allow work and materials to proceed without separate bidding; exhibit B would allow Mammoth to perform the construction administration and builds on the cooperative pricing.

Board members also reviewed capital-outlay projections prepared by the finance committee. Those projections included a $3,000,000 assumption for the project in a five-year planning model. Finance staff said, under that scenario, the district's expenditures would exceed revenues for two years before fund balance began to rebuild in subsequent years; staff said the projections assume modest annual growth in capital outlay revenues from new growth and inflation.

The board moved to approve the Mammoth agreement (exhibits A and B) for design services and to allow Mammoth to be the design-builder if the district later authorized construction. The motion carried by voice vote.