County receives progress updates on Central Pender Park, Hampstead Kiwanis Park and Abbey Nature Preserve
Summary
Contractors told Pender County commissioners on June 2 that Central Pender Park work is ongoing with a new completion target in September, Kiwanis Park Phase 4 is progressing and potentially ahead of schedule, and Abbey Nature Preserve has completed construction drawings and expects bidding this fall.
Pender County staff and contractors gave the June 2 board an update on three capital projects: Central Pender Park, Hampstead Kiwanis Park Phase 4, and the Abbey Nature Preserve.
Central Pender Park: Waters Construction’s representative (introduced as Bishop Williams) reported ongoing site work including driveway, stone base, installation of a 6‑inch fire line and a 3‑inch water supply line, and that the concession building had been roughed in with gang restrooms. Williams said recent rain events added schedule risk and that the contractor had submitted a change order adding 37 days, moving the projected completion date to Sept. 11. County staff said most…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat