Board approves stadium video-board change orders and multiple facility projects totaling roughly $212,000
Summary
The board approved change orders and construction agreements for Bishop Stadium video board electrical work and signage, Lincoln Education Center parking engineering, Northview gym fixture replacement and Seaco Park improvements; each item passed unanimously.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The Manhattan-Ogden USD 383 Board of Education approved several facilities and construction items May 20.
Bishop Stadium video board change orders: The board accepted donations and approved change orders to complete electrical and signage work for the new video board. Greg moved and Christine seconded a motion to accept a change order from Economy Electric in the amount of $14,975 and a change order from JSI (JS sign/awning) in the amount of $3,900; the board approved the motion 6-0.
Lincoln Education Center Points Avenue parking engineering: The board approved BG Consultants of Manhattan for engineering services for the Lincoln Education Center Points Avenue parking project in the amount of $34,500 (motion by Greg, second by Kurt; vote 6-0). The project would expand parking along Points Avenue by approximately 22 spaces.
Northview Elementary gymnasium fixture replacement: The board approved a proposal from SOPA Inc. of Wichita for fixture replacement in the Northview gymnasium for $30,402 (motion by Carla, second by Jamie; vote 6-0).
Seaco Park improvements: The board approved a construction agreement with BHS Construction of Manhattan for Seaco Park improvements in the amount of $133,464 (motion by Christine, second by Greg; vote 6-0). Board discussion indicated some work already underway and that city/district cost-sharing had been part of earlier planning.
All projects were approved by roll call vote 6-0 at the May 20 meeting; staff will return with implementation timelines and reporting on change-order impacts.