Construction update: bond sales, generator options and approved reroof and portable reconnection projects
Summary
District staff reported on bond sales and multiple construction projects, proposed backup generator options and won board approval to reroof Liberty Hill Middle School and reconnect portables at Santa Rita Middle School.
Liberty Hill ISD construction staff reported progress on multiple bond‑funded projects, proposed options for campus emergency power and won board approval on two immediate facilities actions.
Bond and project status: The district reported it has spent or encumbered about 98.5% of its 2021 bond ($491.7 million authorized), with $7.1 million unallocated and $6 million of board‑approved projects pending. The district completed three bond sales in the 2023 series totaling $317 million; cash received to date for the first two sales is approximately $192.44 million and about $140 million has been spent or encumbered against that cash.
Reroof Liberty Hill Middle School: Construction staff presented a recommendation to replace the school’s existing standing‑seam metal roof with a fully adhered membrane system (TPO) over two layers of insulation and a cover board to address…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat