Commissioners approve $11.45 million HMA overlay contract; state funds cover safety upgrades, county covers nonparticipating work

3382591 · May 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board authorized signing a KDOT-administered contract for the HMA 1095 overlay project, approving the $11,449,086.18 contract; KDOT funds will cover safety work while the county will pay for nonparticipating patching and overlay work from road funds.

Linn County commissioners approved moving forward with a county road resurfacing contract on May 19 to carry out a Highway 1095 HMA overlay project estimated at $11,449,086.18.

A KDOT representative and county staff briefed the board that the state’s funding (about $365,000) covers safety improvements such as striping and signing, while the county is responsible for nonparticipating work — chiefly patching and the asphalt overlay. Staff described the state estimate as conservative: “the state had, just based on our previous protocols, wanted us to include 5% of the road to be patched. ... we think it's much more under 1% of the road to be patched,” a county project presenter said, and suggested preparing for roughly $200,000 of patching as a high-end estimate.

The county engineer and staff said the project covers about 5.2 miles and that funds for the county portion are available in the Road & Bridge budget and equipment reserve. Commissioner discussion focused on ensuring appropriate budget appropriation before signing; county staff confirmed there is over $1 million in available funds for resurfacing and reserve purposes and recommended placing the agreement on the next meeting agenda to finalize signatures.

Commissioner Johnson signed the contract estimate during the meeting; the board then made a formal motion and voted to approve the HMA 1095 overlay project by Peppercorn for $11,449,086.18. Commissioners asked Road & Bridge staff (Todd Mueller and Jesse) to appear at the next meeting to confirm funds and discuss additional roads if budget allows.

Action: motion to approve contract for the HMA 1095 overlay project for $11,449,086.18; motion moved, seconded, and approved (voice vote recorded as "Aye").