Governing board approves guaranteed-maximum price for Tumbleweed parking lot and bus turnaround

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Washington Elementary School District governing board approved a guaranteed-maximum price (GMP) award to H and B Builders to complete parking-lot and bus-turnaround work at Tumbleweed after a brief presentation from district staff; the motion passed by voice vote.

At its May 22 regular meeting, the Washington Elementary School District Governing Board approved a guaranteed-maximum price for parking-lot renovations and a bus turnaround at Tumbleweed, awarding the work to H and B Builders under RFQ 24.025.

The board’s motion followed a presentation by Daniel Bridal, who told the board administration recommended approval of the GMP so H and B Builders could finish the Tumbleweed parking lot and bus-turnaround lane. Bridal said Ryan from H and B Builders was present for questions.

Board President Kyle Clayton moved to award the GMP; a second was made and the board voted by voice to approve the award. The agenda item reference lists the procurement as RFQ 24.025, Construction Manager at Risk services for parking-lot renovations at Tumbleweed.

The vote was recorded on the transcript as a voice vote with the chair calling for favor and saying the motion passed. The board did not record a roll-call tally in the public portion of the meeting transcript.

No timeline, contract value, or contingency figures were discussed on the public record during the presentation, and none are specified in the meeting materials presented to the board.

The board moved on to other business after the vote.