Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Smart Metering topic

No spam. Unsubscribe anytime.

Power department reviews Eaton AMI contract; meters expected months after final signature

5109139 · June 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said Hurricane is finalizing a contract with Eaton for advanced metering infrastructure (AMI); once signed, project work and gateway installs precede about a 6–8 month window before meters are placed. The department will need a resolution to update the fee schedule to account for new meter types.

Hurricane City Power staff updated the board on negotiations with Eaton for an advanced metering infrastructure (AMI) system. Staff said the contract is under review; once finalized and signed, Eaton’s timeline suggests about six to eight months before the utility can place meters on customer services. In the interim, staff will install gateways and complete software and training tasks.

Staff and board discussed contract language: members said some commitments made during presentations were not included in the draft contract, and staff will seek those commitments in revisions. Staff noted the project will require changes to the city’s fee schedule — a resolution will be needed to update rates and the fee schedule to reflect new meter types and service charges.

Cost estimates were discussed informally. One presenter said an initial estimate is roughly $2.5 million (staff later asked Eaton to refine and reduce the figure). No final contract value was approved during the meeting; staff said they would return with a final contract after internal review and negotiation.