City staff report: power poles removed, Trader Joe's and Panera activity, Riverside Flats discussions continue
Summary
City staff reported removal of power poles on South Weber Drive and Century Way, said Trader Joe's site work is starting, and provided updates on Panera, the RC Willey site and the Riverside Flats project. Officials said a UDOT-mandated island was installed near the future Panera site.
Get email alerts on the Development Infrastructure topic
No spam. Unsubscribe anytime.
City development staff told the Riverdale City Council on May 20 that utility poles blocking a travel corridor have been removed and several commercial and residential projects are progressing.
Brandon Cooper (Community Development) reported that the power poles on South Weber Drive and Century Way were removed as of Sunday, resolving a safety issue that had caused some local outages. "That safety issue has been resolved," Cooper said.
Cooper provided project updates: he said Trader Joe's is "commencing with the things that they need to commence with" and that Panera's site work was delayed but that July remained the contractor's estimated opening month. He also said the RC Willey building had renewed interest from prospective users (proposed uses not specified) and that the Riverside Flats project team has been meeting with city staff to work toward a mutually acceptable resolution.
Cooper told the council that UDOT required an island in the middle of Riverdale Road near the Panera site; staff pushed back but were unsuccessful. "If you're coming down out of the terrace, don't cut that too sharp or you're gonna be going over a bump right there," he said, and clarified the island is a UDOT mandate, not a city design.
Why it matters: The removal of the power poles addresses a safety and reliability concern; updates on Trader Joe's, Panera and other sites indicate ongoing commercial development that could affect traffic, local services and future tax receipts. City staff said they are continuing negotiations on Riverside Flats to find a resolution acceptable to all parties.
Council and staff said there are no confirmed dates yet for specific tenants beyond the contractor-provided estimate for Panera; Cooper said he had been told Panera's estimated opening was July but that site delays could change that timing. No formal council action was taken on development items at this meeting.