Council approves $80,000 contract amendment for SR‑162 construction management

3411607 · May 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved an $80,000 amendment to Ghirardelli Associates’ construction management contract for the State Route 162 project to cover extended work, night shifts and design change orders.

City staff told the council the State Route 162 project is complete and that Ghirardelli Associates, the construction-management firm hired in March 2023, requested an $80,000 contract amendment to cover additional construction-management costs.

Staff said the original contract was about $913,000 and the $80,000 amendment equals roughly 8.7% of that amount and remains under a 10% contingency. Reasons cited for the overrun included schedule extensions (the project was bid for 186 days but required more than 258 days), expanded night work across the project rather than at only two intersections, 61 requests for information (RFIs) that led to significant design changes, and weather delays. Staff also said the work generated seven large change orders.

Moji Narvar, identified at the meeting as the Ghirardelli resident engineer and project manager, was available for council questions.

The council moved, seconded and voted unanimously to approve the $80,000 amendment.

Ending: Staff said they would execute the amendment and close out the project file.