Easton Elementary renovation enters phase three; gym and finishing work delayed a few weeks
5597458 · May 30, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
District staff reported the Easton Elementary renovation has substantial work complete, furniture for phases 1 and 2 installed, one classroom trailer remains, gym floor curing delays could push completion a few weeks but overall opening for students expected on schedule.
Mr. Schaffer and district staff updated the board on Easton Elementary renovations and related site work during the Aug. 18 work session. Staff said much of the work for phases 1 and 2 is complete, new furniture for those phases has arrived and will be inspected, and the project is entering phase…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans