Chickasha council approves consulting, TIF counsel, engineering agreement and construction payments; one abstention and two no votes recorded
Summary
The council authorized a consulting engagement, retained TIF counsel, approved a master services agreement with an engineering firm, and approved a contractor payment and a sewer change order; votes were recorded for each item.
Get email alerts on the Council Votes Contracts topic
No spam. Unsubscribe anytime.
The Chickasha City Council approved several routine and development-related items during its regular meeting, including authorization for economic-development consulting, retention of tax-increment finance (TIF) counsel, a master services agreement for engineering services and payments for capital projects.
Key outcomes:
- The council approved a consulting engagement agreement with Co Align Group to give city staff the ability to engage the firm during upcoming economic-development activity. The motion passed by roll call with one recorded no vote (Burris). Supporters said the authorization only gives the city manager the ability to negotiate and does not obligate the city to proceed without later council approval.
- The council approved an agreement for TIF counsel services with The Public Finance and Law Group, P.L.L.C., and authorized the mayor to execute the agreement. The motion passed by roll call with a single no vote recorded (Burris).
- The council approved a master services agreement (MSA) with Half Associates Inc. for on-call professional engineering services. The MSA authorizes task orders that will include specific fee schedules; the council approved the agreement and the fees shown to council members. The vote recorded one abstention (Burris) and otherwise passed.
- The council approved Pay Application No. 1 in the amount of $25,650 to W.W. Builders Inc. for the Chickasha Police Department canopy project. The payment covers architect and engineering services and was approved by roll call.
- At the Chickasha Municipal Authority meeting, the authority approved Change Order No. 1 for CMA-2501, sanitary sewer main replacement on Colorado Avenue and Fourth Street, in the amount of $167,819.44. Staff said the project is nearing final inspection.
Council discussion included concerns about timing โ several members asked whether authorization to hire consultants was premature ahead of an anticipated announcement and asked whether agreements would obligate the city to proceed. City Manager Jim Crosby and other staff said authorization would allow staff to move quickly if development opportunities materialize but that any contract or expenditure would return to council for approval.
Votes and roll-call tallies are summarized below; official minutes should be consulted for the full record.