Commissioner panel recommends approval for Bringhurst Village phases 1 and 2; conditions and timeline discussed
Summary
The commission voted to recommend approval of construction drawings for phases 1 and 2 of the Bringhurst Village development, while stressing the recommendation should not be read as approval of the project's full phasing plan and requesting that utilities and mixed-use timing be addressed in future submittals.
Get email alerts on the Major Development Phasing topic
No spam. Unsubscribe anytime.
The Hyde Park Planning Commission recommended approval May 21 of the construction plans for phases 1 and 2 of the Bringhurst Village development, while clarifying the decision does not constitute approval of the overall phasing plan or of future phases.
Marcus and the developerrepresentative described phases 1 and 2 as primarily residential: roughly 200 townhomes and about 50 apartment units are included in the developerpresentation for the full site, while the immediate submission covered detailed construction drawings only for phases 1 and 2. The developer said bringing water and sewer utilities up the eastern edge of the site is a key priority: the developer proposes to construct sewer and a water loop, and agreed to upsize portions of the water line to 10-inch pipe on the eastern alignment to improve long-term capacity for later development.
The developer also said the project would dedicate right-of-way for a planned Wolfpack Way and construct utilities that staff and the developer said are needed before commercial and mixed-use development on the site can move forward. The developer explained that commercial partners are unlikely to finance mixed-use buildings until residential phases begin and utilities are in place.
Commissioners pressed the developer on several topics: (1) access and fire-code requirements (primary access approved by UDOT, phased safety measures and a gated fire apparatus access are proposed if unit counts exceed thresholds); (2) open-space distribution and timing of park areas (developer said open space is distributed across phases but some park elements come later); (3) utilities sizing and phasing (developer said phases 1 and 2 would install looping water and sewer and 10-inch eastern pipes to facilitate later phases); (4) whether phasing would be rigid or could be reordered; and (5) how the city should treat future submittals so commercial phases cannot be deferred indefinitely.
Multiple commissioners and staff noted the mixed-use zoning includes a provision that no phase be solely residential unless at least 50% of required commercial area was built earlier, and commissioners said they would expect future phases to demonstrate timely progress on mixed-use commitments. The commission added a clear statement to the recommendation: approval of phases 1 and 2 should not be interpreted as recommendation of the entire phasing plan.
A motion to recommend approval of phases 1 and 2, amended to note it was not an endorsement of the entire phasing plan and that utilities must be provided as proposed, passed on a voice vote; commissioners recorded "aye." The developer and staff indicated the work to install utilities and complete the initial phases is expected to take about a year for the utilities and roughly 3to5 years to build out the initial residential build-out, with full project completion estimated in the 4to7-year range depending on market conditions.
The commission clarified that each future phase will require separate construction-plan submittals and review; the city retains the ability to require mixed-use components before allowing additional purely residential phases.