Creekview construction 67% complete; district awards AG/ROTC building contract with September substantial completion target
Summary
Trustees received a construction update showing Creekview High School at about 67% completion and were informed the Medina Valley High School AG/ROTC building contract was awarded to W.R. Griggs at a contract amount of $11,500,000 with a targeted substantial completion of Sept. 30, 2025.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
District staff updated trustees May 27 on major capital projects including Creekview High School and the Medina Valley High School AG/ROTC facility.
Rafael Barajas (construction brief) told trustees the Creekview High School project was approximately 67% complete, a roughly 3-percentage-point increase from the prior month's report. Exterior work includes roofing cap sheets, site concrete and delineation of additional parking areas. Athletic-field work is underway with liners, final grading, storm drains and areas prepared for field events such as high jump, long jump and pole vault.
An internal update on the interior work noted specialty installations in classroom and lab areas, restroom tile and partitions, painting and ceiling framing in the library and cafeteria areas, and progress in both the auxiliary and competition gyms; court installation is expected in July-August as HVAC conditioning is phased in.
On the Medina Valley High School AG/ROTC project, staff reported the board awarded the contract to W.R. Griggs. The district reported a contract amount of $11,500,000 and a target substantial-completion date of Sept. 30, 2025. The presentation said CPS (the local electric utility) had installed poles and primary service lines south of the property, and Griggs had tied the primary into a new transformer to feed the campus. District staff noted no pay application had yet been received for the first month and said percent-complete reporting would be in the next board packet.
Staff also reported relocation of three portables previously south of the band hall to a location outside Building 200 for future middle-school use.
What this means - Creekview: 67% complete; exterior flatwork and athletic field work are active; interior finishes progressing with HVAC and court scheduling planned for summer. - AG/ROTC building: contract awarded to W.R. Griggs at $11,500,000 with a Sept. 30, 2025 target for substantial completion; CPS service work is substantially complete.
Next steps District staff will provide percentage-complete information for the AG/ROTC project at the next board meeting and continue to track remaining change orders and 2024 bond allocations tied to stadium and athletic improvements.