Council approves $382,123 change order for Forest Road project to stabilize excavation at Uptown parking garage
Summary
The Sedona City Council approved change order No. 15 for the Forest Road Connection project, adding $382,123 for excavation and soil‑nailing slope stabilization associated with the Uptown parking garage; staff said the work is covered by project contingency.
Sedona — The City Council approved a $382,123 construction change order (No. 15) to the Forest Road Connection contract to support additional excavation and soil‑nailing slope stabilization at the Uptown parking garage site.
Public Works Director Kurt Harris and project manager Bob Welch told council the unexpected subsurface conditions discovered during excavation required additional stabilization work. Harris said the cost will be charged to the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat